Client Name:
Project Type:

Project brief

  • Cat scan, locate and re-direct existing services within bank,
  • Excavate existing bank, segregate waste and removal from site.
  • Management and execution of Temporary Works and Temporary Works Designs.
  • Install sheet piles to perimeter of excavations.
  • Form new steel reinforcing and formworks for new 3.5m high RC retaining wall excavate and pour 3m deep foundations,
  • Construct new steel framed 2 storey OHL building consisting of offices, stores and workshops.
  • Construct new foul and grey water pumping station.
  • Fit out new building including M&E works and handover to client.

Project duration 9 months.
Ducron Principal Contractor.